Important Role of Consultants and Contractors with their
Responsibilities
In planning and Execution of work, The Architect
has also fulfills Government formalities before Commencement (Raja Chithi), He
also co-ordinate with various agencies. As same Structure designer play his
role perfect for Structural portion. Understand with their responsible
points :
è
Architect –
-
Understand Requirement from the client / Builder
-
Prepare Initial Sketches or Drawing for that
-
Guideline for Brochures
-
Prepare Drawing and permit from Municipal
Corporation as per Bye-Laws
-
Submit Plans for NOC Clearance – Drainage
Department, Road Department and Other Department
-
Detail Drawing with Specifications and dimensions
for Sanction by Municipal Corporation
-
Physical cross check at site in regular basis
-
Prepare Calculations for Taxes, Fees and Charges of
Government
-
Suggest Material Specification
-
Settle the dispute bills of Contractors
-
Meetings with Government Authorities, Contractors
and Agencies for work
-
Prepare the Model Building of the Project
-
Give Amenities Drawing of project
è Structural Designer –
-
Workout RCC design based Strata and Architectural
Drawing
-
Checking of Strata of Footing, Reinforcement, Visit
to the Site, Quality of the Concrete, Estimate of require Structure Steel and
RCC Work
-
Inspection of the trial pit for check Strata
-
Checking Strata for footing pits basement before
laying foundation PCC
-
Checking Reinforcement at every stages of RCC work
-
Checking footing concreting
-
Precautionary measures for work near existing
structure
-
Checking Plinth Filling before floor PCC work
-
Inspection of any damage work
-
Inspection of Expansion Joints
-
Critical Structures –
Lift Shaft bottom slab
Machine Foundation
Slab on Nalla and Culverts
Staircase and Ladders
Decorative Towers, RCC Grills and Floating Columns
Light Weight Masonry
Water proofing of structures
Expansion Joints
è Plumbing Consultant –
-
Water supply system
-
Internal pipe fittings
-
Plumbing and sanitary work
-
Drainage disposal layout
-
Strom Water
-
Drain details
-
Septic Tank
-
Underground Water Tank
-
Overhead water Tank
-
Boosting system details
-
Fire Fighting System
Implements
-
Materials – GI, CI, PVC, uPVC, cPVC pipes and Its
fittings with Solutions
-
Solve and Repairing work / Leakages and seepage
works
-
Pump details
-
Swimming pool water supplying and
outlet system
-
Check Pressure after done rough work of piping in
Unit
-
NOC Should be Issued by the plumbing consultant at
Stages of works-
Plinth and Parking Levels
Strom Water and Drainage arrangements
Sewer line to laid in and out side of project
Conceal Piping work as per stages of construction –
Floors and Plaster
Ground Drainage network and All Main hole chambers
connections
Invert level of Septic Tank and Soak pit
Terrace Piping work
Overhead water Tank inlet and outlet
Underground
Water Tank piping work
è Electrical Consultant –
-
Submit the layout drawing of electrical cable
distribution system
-
Study of require load 3 Phase
-
Main line – Transformer – Feeder Pillars – Switch
Gear – Bus bar – Meter
-
Distribution of power supply
-
Earthling work (GI 1” Patty)
-
Cross check after done meter fittings – Unit wise
è Road Work Consultant –
-
Mark Roads
-
Types of Road depending on Strata, Geography and
Soil of land
-
Check Road level with Dumpy Level and Staff
-
Section Drawing of road with details
-
Details of Rain water gutter or trenches, Drainage
Mainholes with Its Covers, Inspection Chambers, Strom Water Drains,
-
Proper slops of roads
-
Mark location of trees and Electric poles along
with road
-
Give NOC for the following work of road –
Layout
All underground conducts and Drainage lines
Filling, Compaction, Level, Thickness and Slopes of
the road
è Water Proofing Consultant –
-
Decide Type of Water Proofing for Various work in
construction
-
Water proofing for expansion joints
-
Check Physically at site
-
After Base coat – Spout fixing and grouting
-
After laying Brickbat coba before final finishing
-
Final testing of flooring by water
è Land Scape Consultant –
-
Plan for landscaping work
-
Stage of work for gardening and plantation
according to the project
-
Drawing of Play Ground and Its Equipment, Types of
Trees, Sand Pits
-
Estimate for Landscaping
-
Lawns and plants in garden
-
Appoint Gardeners for protect plantation and proper
grow
-
Water Supply arrangement for watering in the
Landscape areas
-
Pumping System and Its Electric connection
-
Provision of Draining water and Fountains
-
Design for Fountain and Estimate and Maintenance
è Swimming pool Consultant –
-
Specify Size and Capacity of Swimming pool
-
Water Supply Provision
-
Water Outlet Provision
-
Electricity arrangement
-
Filtration Plant
-
Drainage Arrangement
-
Plumbing work
-
Construction Details of Swimming pool
-
Purify Water / Re use water for Swimming pool
-
Protective Fencing surrounding the swimming pool
-
Changing room, Bathing place, water sports and
Swimming shout
No comments: